The Station

Project Details

Client: 

Builden

Sector:

Commercial

Location:

South Perth, WA

Project Date:

January 2023 – June 2023

Scope:

Boxed out 350mm over full site including battering to perimeters to protect existing structures.
Removed guide wall and exported concrete off-site.
Graded, watered and compacted sand pad and carried out NATA certification.
Imported 400T of recycled road base and constructed a 350mm thick piling platform with certified KPA report.
Worked alongside the piling rig and crew carrying out cropping method.
Exported a total of 975m3 of pilling spoil.
Excavated the front side of piles and cleaned off excess concrete.
Jack hammered and cleaned off pile tops ready for reo install.
Backfilled and compacted excavations to blinding to allow for capping beam formation.
Deconstructed piling platform and exported materials offsite.
carried out bulk excavations under steel braces to the underside of FFL.
pressure washed and cleaned down piles.
Excavated all edge thickenings.
Carried out the final trim of the ground slab. Watered and rolled and carried out NATA certification.