Project Details
Client:
BBS Developments
Sector:
Residential
Project Date:
November 2021 – October 2022
Scope:
Clear site, strip back topsoil and dispose of off-site.
Import road base and construct multistage piling platform.
Provide KPA report by NATA approved facility.
Carry out wet cropping method to foundation and perimeter piles.
Prepare capping beams.
Carry out bulk excavation to the underside of SSL and export approx. 9000m3 of sand.
Completed detailed excavations.
Pressure wash and clean down piles.
Carry out final trim and provide NATA approved certification.
Completed verge works and surrounding clean up.
Previous slide
Next slide