Project Details:

Location: Cunderdin Health Centre, Cunderdin WA

Services Completed: October 2017 – September 2018

Project Status: Completed

Main Earthworks:
The services completed for the main earthworks included; vegetation topsoil removal, demolition and site clearing, removal of trees, 4,200 tonnes of tested and approved imported clean fill to build main building pad, footings for main building pad and expansion joints, compaction and relevant testing.

Carpark:
The services completed for the 3,500m2 carpark included; Roadworks subgrade prep in H1 material, complex compaction and cuts, importation of 1,700 tonnes of imported gravel, 370 tonne of imported road base, prime seal, supply and lay of asphalt, kerbing, line marking and signs for the completion of the Health Centre carpark.